Wiring.While we could wire a limited number of
nodes ourselves (10?), wiring of the full testbed has to happen
before the testbed is maximally useful. Jay has references from Dave
for people who
will, at a minimum, make cables. Not sure if they will do a
big installation job. Some thought given to telecommunications
but concern about (1) backlog and (2) cost. If wiring
is not done correctly, we will be paying the
price for a long time to come. As an alternative, perhaps we could
hire a professional to come out and show us the best way to string
the wires.Steve has found that the rails on the racks are very
difficult to work with because they're easily misaligned. Note that
this adds time to testbed setup.